Closures for Week of May 22, 2016
For detailed closure and detour information, visit the project
Google map or click on the map icon below. Please note, the speed limit on the SR-23 and US 101 freeways within the project area has been reduced to 55 miles per hour. Motorists are reminded to slow down within the project corridor, use caution and observe all posted signage while traveling through the construction zone.    

Daytime Closure of Northbound 101 Hampshire Road Off-Ramp | Thursday, May 26 & Tuesday, May 31
Crews will close the northbound US 101 Hampshire Road off-ramp on Thursday, May 26 and Tuesday, May 31, between 8 a.m. and 2 p.m. These closures are needed as crews conduct work to install a new overhead sign at this location. A portable message board will be placed on northbound 101 at Lindero Canyon, to notify motorists in advance of the ramp closure. Motorists can use the Lindero Canyon, Westlake Boulevard or Rancho Road off-ramps to exit northbound 101 while the Hampshire Road off-ramp is closed.

US 101 Nighttime Lane, Ramp & Connector Closures  
Crews will close one lane along northbound US 101 from Westlake Boulevard to the SR-23 connector, nightly between 7 p.m. and 6 a.m., Monday, May 23 through Wednesday, May 25.

In addition, both northbound on-ramps to US 101 at Westlake Boulevard will be closed during this timeframe, as well as the Hampshire Road northbound on- and off-ramps and the northbound US 101 connector to the northbound SR-23.

DETOUR: At least one lane along northbound US 101 will remain open at all times. Please visit the project Google map for more information regarding scheduled closures.

In addition, crews will close one lane along northbound US 101 from Westlake Boulevard to the SR-23 connector, nightly between 7 p.m. and 6 a.m., Wednesday, May 18 through Friday, May 20. Both northbound on-ramps to US 101 at Westlake Boulevard will also be closed during this timeframe, as well as the Hampshire Road northbound on- and off-ramps and the northbound US 101 connector to the northbound SR-23.

Please visit the project Google map for detailed detour information more information regarding scheduled closures.

DISCLAIMER: Please be advised, dates and times are subject to change due to unforeseen operational factors or inclement weather.


Long-Term Construction Impacts

While most construction activity will take place at night or during off-peak hours, lanes have been reduced in a few locations in order to facilitate construction activity. Intermittent nighttime lane closures on the northbound US 101 and surrounding on- and off-ramps may be required over the next few weeks, although no closures are currently scheduled. To avoid congestion and minimize delays related to this work, consider alternative routes and allow extra time to reach your destination if your trip involves the following routes:

  • Northbound Hampshire Road to Northbound US 101 on-ramp has been reduced to one left turn lane, 24/7

 
       View closures on Google Maps